    AI production planning takes 91.6% less time at Atlas Copco

    Atlas Copco's Portable Air division had Superlinear build an open-source optimizer that plans its compressor assembly lines and gives sales representatives a lead time while the customer is still in the meeting.

    Atlas CopcoBelgium and United StatesIndustrial machinery and equipmentIn production
    Scale
    2 production sites in Belgium and one in the USA
    Scenario
    Assembly line production planning optimization
    Business function
    Manufacturing and quality
    Who built it
    Built by a partner (Superlinear and KU Leuven)
    Human oversight
    Assists people
    Time to production
    2 months
    Organization
    Enterprise, 10,000 to 99,999 employees
    AI types
    Optimization

    Sources and their publishers

    This case study draws on reporting by the following publishers. Enterprise AI Case Studies combined these accounts and added its own explanation. The reporting, and every passage quoted from it, belongs to whoever published or supplied it.

    1. Superlinear

    2. Atlas Copco Group

    3. COIN-OR Foundation

    4. Gurobi Optimization

    tl;drThe optimizer plans in 91.6% less time than a planner, with 9.0% more orders delivered on time.See the results

    View the solutionBuild this solution yourself

    Atlas Copco’s Portable Air division uses an AI optimizer to plan the assembly lines where it builds mobile compressors1. Superlinear built the optimizer on COIN-OR CBC, an open-source solver1.

    Production planners use the optimizer to promise delivery dates for new orders and to reevaluate the current plan1. Sales representatives get a lead time from it while they are still in the meeting with the customer1.

    The optimizer spends 91.6% less time on a plan than a human planner, and the number of orders delivered on time rose by 9.0%1. It runs at production sites in Belgium and the United States1.

    Before the deployment

    Production planning in the Portable Air division allocated employees, materials, and machinery to the assembly lines1. The division assembles complex products to fit each customer’s requirements, and Atlas Copco designs and produces most of its compressors in Wilrijk, Belgium1. Superlinear worked on the project with Atlas Copco’s Power Technique business area1.

    The planning process had the following problems:

    • Effort: Production planning required a lot of time, resources, and human effort1.
    • Constant change: The plan kept changing, because some orders took more time than foreseen and new orders came in1.
    • Licensing cost: Atlas Copco used a commercial solver with a steep licensing cost. A solver of that kind becomes expensive when it’s implemented at different sites, divisions, and countries1.
    • Delivery promises: Customers needed accurate information about the status of their orders. Atlas Copco wanted to give sales real-time insight into the capabilities of the production facility1.

    What was built

    The optimizer generates production plans for the Portable Air assembly lines, for production planners and for sales engineers1. The work is divided as follows:

    • Optimizer: Computes a plan that takes the parameters and variables of production planning into account, which include item availability, inventory capacity, employees, and machinery1.
    • Planning system: Contains the optimizer, which is integrated into it. Atlas Copco developed this system itself1.
    • Sales system: Receives the optimizer’s output through a real-time integration1.
    • Production planners: Use the optimizer to promise delivery dates for new orders. They also use it to reevaluate whether the current plan meets customer expectations and commitments1.
    • Sales representatives: Give the customer a lead time immediately, during the meeting1.
    • Atlas Copco’s own team: Can modify and update the optimizer inside Atlas Copco’s own system. Superlinear showed the team how to tailor it for further applications1.

    “It enables us to communicate faster and better with our customers, formulating commitments we can keep. At the same time, the solver increases the effectiveness of our customer contacts.”

    Bart Vercammen, team leader manufacturing systems and processes at Atlas Copco1

    Alternatives considered

    Atlas Copco required a solution implemented with 100% open-source software1. The two options compared as follows:

    • Commercial solver: Atlas Copco already used one for production planning. Its licensing cost rises with each site, division, and country that implements it1.
    • Open-source solver: Atlas Copco can integrate it into its own systems and keep improving it. Superlinear and Atlas Copco chose COIN-OR CBC for the project1.

    Rollout

    Superlinear developed the optimizer in collaboration with professor Seppe vanden Broucke of KU Leuven1. The work went through the following phases:

    • First sprint: After 2 weeks, the first version included a complete mathematical and AI model1.
    • Iterations: After 2 months of work and three iterations, the optimizer was ready for full rollout. The iterations changed the optimization problem definition, the solver parameters, and the way the solution was compiled, which produced a 100-fold speedup1.
    • Production: The optimizer runs at two Atlas Copco production sites in Belgium and one in the United States1.
    • Planned expansion: Atlas Copco plans to roll the optimizer out to other countries and divisions1.

    Technology and architecture

    Figure 1How the optimizer serves planners and sales at Atlas Copco
    How the optimizer serves planners and sales at Atlas CopcoOrder lines and the constraints of the assembly line, such as item availability, inventory capacity, employees and machinery, go into the production planning optimizer, which runs on the open-source solver COIN-OR CBC. The optimizer passes plans and delivery dates to the planning system that Atlas Copco developed. Production planners use the planning system to promise dates and to reevaluate the plan. The optimizer also passes lead times in real time to the sales system, where sales representatives read them during a customer meeting. No part is inferred.new and planned orders (data) · Documented in source [1]items, capacity, staff (data) · Documented in source [1]plans and delivery dates (data) · Documented in source [1]plan to reevaluate (handoff to people) · Documented in source [1]real-time lead times (data) · Documented in source [1]lead time (handoff to people) · Documented in source [1]ATLAS COPCO SYSTEMSOrder lines · Data · Documented in source [1]DATAOrder linesAssembly line constraints · Data · Documented in source [1]DATAAssembly lineconstraintsOptimizer on COIN-OR CBC · AI model · Documented in sources [1] [3]AI MODELOptimizer onCOIN-OR CBCPlanning system · System · Documented in source [1]SYSTEMPlanningsystemSales system · System · Documented in source [1]SYSTEMSales systemProduction planners · Person · Documented in source [1]PERSONProductionplannersSales representatives · Person · Documented in source [1]PERSONSalesrepresentativesnew andplanned ordersitems,capacity, staffplans anddelivery datesplan toreevaluatereal-timelead timeslead timeHow the optimizer serves planners and sales at Atlas CopcoOrder lines and the constraints of the assembly line, such as item availability, inventory capacity, employees and machinery, go into the production planning optimizer, which runs on the open-source solver COIN-OR CBC. The optimizer passes plans and delivery dates to the planning system that Atlas Copco developed. Production planners use the planning system to promise dates and to reevaluate the plan. The optimizer also passes lead times in real time to the sales system, where sales representatives read them during a customer meeting. No part is inferred.new and planned orders (data) · Documented in source [1]items, capacity, staff (data) · Documented in source [1]plans and delivery dates (data) · Documented in source [1]plan to reevaluate (handoff to people) · Documented in source [1]real-time lead times (data) · Documented in source [1]lead time (handoff to people) · Documented in source [1]ATLAS COPCO SYSTEMSOrder lines · Data · Documented in source [1]DATAOrder linesAssembly line constraints · Data · Documented in source [1]DATAAssembly lineconstraintsOptimizer on COIN-OR CBC · AI model · Documented in sources [1] [3]AI MODELOptimizer onCOIN-OR CBCPlanning system · System · Documented in source [1]SYSTEMPlanning systemSales system · System · Documented in source [1]SYSTEMSales systemProduction planners · Person · Documented in source [1]PERSONProduction plannersSales representatives · Person · Documented in source [1]PERSONSales representativesnew and planned ordersitems, capacity, staffplans and delivery datesplan to reevaluatereal-time lead timeslead time
    • AI component
    • Data
    • Handoff to people
    Sources [1][3]
    The optimizer turns order lines and line constraints into plans for planners and lead times for sales.

    The following table lists the components of the solution.

    Layer What they used Role Source
    Optimizer Production planning optimizer Holds the mathematical model of the assembly line’s constraints and computes plans and delivery dates 1
    Framework or library COIN-OR CBC Solves the planning problem as an open-source solver, with parameters tuned to this task 1, 3
    Service API Optimizer API Fits the optimizer into Atlas Copco’s existing processes 1
    Business or operational system Planning system Contains the integrated optimizer. Atlas Copco developed it 1
    Business or operational system Sales system Receives lead times in real time 1

    COIN-OR CBC is an open-source mixed integer linear programming solver that an application can call as a library3. In this deployment, it solves the planning problem that Superlinear defined, with solver parameters that Superlinear tuned to that problem1.

    The optimizer is fully parameterized, so that other production facilities with different requirements can adopt it1.

    Data inputs

    The optimizer uses the following data:

    • Order lines: New orders and the orders already in the plan. Each planner is responsible for multiple assembly lines and has several hundred order lines in the plan at any moment1.
    • Items: The type and number of items that an order needs, and the availability of those items1.
    • Capacity: The inventory capacity, the employees, and the machinery of the assembly line1.

    Integrations

    The optimizer connects to two Atlas Copco systems. It’s integrated into the planning system through an API that fits Atlas Copco’s existing processes1. Its real-time integration with the sales system gives each sales representative the lead time1.

    The Portable Air division developed planning software that draws on the data in its different systems and adds a layer of AI2. The modules of that software cover supply chain transparency, production planning, workforce planning, inventory management, and supply chain simulation2. The planning system that contains the optimizer is most likely this software.

    Results

    The following table lists the published results.

    Metric Before After Scope and timeframe Reported by
    Time spent on planning Not disclosed 91.6% less The optimizer compared with a human planner Superlinear, measured1
    Orders delivered on time Not disclosed 9.0% more Orders delivered on the requested delivery date Superlinear, measured1
    Total days that orders are late Not disclosed 17.2% fewer Against the first promised delivery date Superlinear, measured1
    Solve time Not disclosed under one minute The majority of planning problems Superlinear, measured1

    The metrics measure the following:

    • Time spent on planning: The time that the optimizer spends on a plan, compared with the time that a human planner spends1.
    • Orders delivered on time: The number of orders that reach the customer on the delivery date that the customer requested1.
    • Total days late: The sum of the days by which orders miss the first delivery date that Atlas Copco promised1.
    • Solve time: The time that the solver takes on one planning problem. Its speed is competitive with commercial solvers1.

    Atlas Copco’s account of the division’s planning software adds two outcomes:

    • Rescheduling: Rescheduling a production line takes minutes or seconds instead of hours2.
    • Award: Atlas Copco gave the Portable Air team that developed the software its 2020 Giulio Mazzalupi Operational Excellence Award2.

    Lessons learned

    The open-source requirement answered the licensing problem. COIN-OR CBC is released as open source under the Eclipse Public License 2.0, and the optimizer’s speed is competitive with commercial solvers1, 3.

    COIN-OR CBC is versatile, but it needs meticulous tuning to the task that it solves1. The optimizer reached its speed only after three iterations on the problem definition, the solver parameters, and the compilation1.

    Parameterization prepared the optimizer for other sites. Bart Vercammen said that the open-source, fully parameterized design makes a rollout possible to facilities where a product-specific focus might bring different requirements1.

    The Portable Air team keeps the work close to its users. It adds features to its planning software in close collaboration with the final users, and Vercammen’s advice is to try an improvement and fix it when it doesn’t work2.

    The percentages and the solve time are Superlinear’s figures, from a customer story that Superlinear labels as earlier work1.

    Case study scorecard

    Sources by publication date

    • Organization 1
    • Vendors and partners 4
    • 4 undated

    Build this solution yourself

    Analysis

    What you need

    To build this solution, you need the following in place:

    • A planning system that can take an optimizer: Atlas Copco had developed its own planning system, and Superlinear integrated the optimizer into it through an API1. Check that your planning system can call one.
    • Constraints as data: The optimizer needs the items, their availability, the inventory capacity, the employees, and the machinery of each line in a form that software can read1.
    • People who can tune a solver: COIN-OR CBC needed three iterations on the problem definition and the solver parameters before rollout, so you need optimization skills on the team1.
    • A link to the sales system: The lead time reaches the customer meeting only because the optimizer integrates with the sales system in real time1.

    Reference architecture

    Scheduling and routing optimization

    A scheduling and routing optimization solution computes who or what goes where, in what order, and when, within the constraints that apply. An optimizer builds a plan from the work, live positions and conditions, and the organization's rules, and rebuilds it as conditions change. Planners approve or finish the plan or steer it through limits, and the people who carry it out can depart from it.

    A check mark shows a building block that this case study's sources document.

    Open the reference architecture

    Others who built it

    • Yutong Bus: The bus maker’s planning system allocates customer orders to 10 production lines, and Gurobi solves its sequence of mixed integer programming problems within 45 minutes4.
    • Kaneka: The chemical manufacturer generates production and cutting plans for polyimide film at its Shiga Plant with MathCutting, which runs on the Gurobi Optimizer5.

    Cite this case study

    Enterprise AI Case Studies. "AI production planning takes 91.6% less time at Atlas Copco." Updated Nov 20, 2026. https://case-studies.ai/case-studies/production-and-quality/PQ-026-production-planning-optimization-atlas-copco/

    @misc{csai-pq-026,
      author = {{Enterprise AI Case Studies}},
      title = {{AI production planning takes 91.6% less time at Atlas Copco}},
      year = {2026},
      note = {Updated 2026-11-20},
      url = {https://case-studies.ai/case-studies/production-and-quality/PQ-026-production-planning-optimization-atlas-copco/}
    }

    Sources

    The following reporting, and every passage quoted from it, belongs to its publisher, not to this site. Sources and ownership

    1. Source 1:

      Superlinear and Atlas Copco optimize production planning with AI

      Partner or vendorSuperlinearAccessed Nov 20, 202620 Nov 2026

      Supporting excerpts (40)
      • Optimizing the production planning of Atlas Copco’s Portable Air manufacturing sites, where complex products are assembled to fit its customers’ requirements.
      • Superlinear developed a software that allows both Production Planners as well as Sales Engineers to quickly generate accurate and optimal production plannings.
      • employing more than 39.000 people around the world
      • The Portable Air division designs, manufactures and markets mobile compressors, including high-pressure boosters, and light demolition handheld tools for industries all over the world.
      • The company conducts ground-breaking research in Wilrijk, Belgium, where most of the compressors sold throughout the world are designed and produced.
      • It allocates employees, materials and machinery while taking multiple, complex variables into account like items availability and production capacity.
      • At the same time, customers need to receive accurate information about the status of their orders.
      • Production planning, therefore, requires a lot of time, resources and human effort.
      • For this project, Superlinear worked with Atlas Copco’s Power Technique business area
      • For its production planning, Atlas Copco was using a commercial solver, which has a steep licensing cost.
      • These types of commercial solvers can quickly become highly expensive if they are to be implemented on different sites, divisions and countries
      • Reducing the human time spent and improve at the same time the number of orders that are delivered on the requested delivery date.
      • The goal was to give sales real-time insight into the capabilities of the production facility.
      • Implemented with 100% Open source software, so that the solver could be integrated into Atlas Copco’s own systems while allowing for easy continuous improvements.
      • Type and number of necessary items, availability of said items, planning, inventory capacity, employees, and machinery needing to be involved, etc.
      • Production planning is continuously changing due to some orders taking more time than foreseen or new orders coming in.
      • Superlinear offered us a flexible and customizable API which slotted seamlessly in our existing processes
      • - Bart Vercammen - Team Leader Manufacturing Systems & Processes at Atlas Copco
      • Superlinear, in collaboration with professor Seppe vanden Broucke (KU Leuven), was able to develop the first sprint of the AI solution after just 2 weeks.
      • That first version included a fully-fledged mathematical and AI model.
      • Superlinear and Atlas Copco set their sights on COIN-OR CBC, an open-source solver for the project.
      • COIN-OR CBC is very versatile, but needs to be meticulously tuned to the specific task that needs to be solved.
      • After 2 months of work and 3 iterations, Superlinear’s AI optimizer was ready to be fully rolled out.
      • The solver offered a 100-fold speedup in 3 versions by iterating on the optimization problem definition, the solver parameters, and the way in which the solution was compiled.
      • Superlinear’s AI-powered optimizer spends 91.6% less time than a human planner, improves the number of orders delivered on time by 9.0%, and reduces the total number of days orders are late versus the first promised delivery date by 17.2%.
      • The software is flexible and can take all the different parameters and variables of production planning into account.
      • The solver speed is competitive with commercial solvers. The majority of problems can be solved in under one minute
      • Superlinear’s optimizer has successfully been integrated into a planning system developed within Atlas Copco.
      • It offers real-time integration with the sales system: the sales representative can now give a lead time immediately, even while still in meeting with the customer.
      • It is used by the production planners in the product company who are each responsible for multiple assembly lines where they have at each moment in time several hundreds of order lines in the planning.
      • The solver helps them to optimally promised delivery dates for new orders and to reevaluate whether the current planning optimally satisfies customer expectations and commitments.
      • Superlinear’s solution is currently implemented at 2 Atlas Copco production sites in Belgium and one in the USA.
      • It can be modified and updated inside Atlas Copco’s own system.
      • It enables us to communicate faster and better with our customers, formulating commitments we can keep. At the same time, the solver increases the effectiveness of our customer contacts.
      • Superlinear’s solution is planned to be rolled out in other countries and divisions at Atlas Copco.
      • As the solution is open source and fully parameterized, it makes it possible to easily roll it out to our other production facilities in Belgium, US, China, Brazil and India where Atlas Copco product-specific focus might result in different requirements.
      • They even took the time to show us how to tailor the solution ourselves for further applications within Atlas Copco
      • we're thrilled to see that the solution provides a significant impact on the number of orders delivered on time while at the same time making the planners' jobs easier
      • - Laurent Sorber - Co-founder and CTO at Superlinear
      • This case reflects earlier work at Superlinear.
    2. Source 2:

      Giulio Mazzalupi Award 2020 - Data-driven efficiency

      OrganizationAtlas Copco Group, Jul 16, 202116 Jul 2021Accessed Nov 20, 202620 Nov 2026

      Supporting excerpts (6)
      • What about a creative software using artificial intelligence to reduce production planning time from hours to seconds? This is exactly what Bart Vercammen, Team Leader Manufacturing Systems & Processes; Rik Van De Velde, VP Manufacturing; and Veerle Van Den Bossche, Program & Team Leader in the Portable Air division developed a few years ago, and for that they were awarded the 2020 Giulio Mazzalupi Operational Excellence Award.
      • By allocating the data available in our different systems and then adding a layer of artificial intelligence, this software helps our production staff make much faster and more accurate decisions for the benefit of our customers.
      • Rescheduling a production line can for example be done in minutes, or even seconds, instead of hours
      • Since then, new modules have been added, focusing on supply chain transparency, production planning, workforce planning, inventory management, supply chain simulation, and more.
      • We are constantly adding new features in close collaboration with the final users.
      • Just try it out and if it doesn’t work, fix it and try again
    3. Source 3:

      Cbc: COIN-OR Branch-and-Cut solver

      Product documentationCOIN-OR FoundationAccessed Nov 20, 202620 Nov 2026

      Supporting excerpts (3)
      • Cbc (Coin-or branch and cut) is an open-source mixed integer linear programming solver written in C++.
      • It can be used as a callable library or using a stand-alone executable.
      • Cbc is written in C++ and is released as open source under the Eclipse Public License 2.0.
    4. Source 4:

      Yutong Bus: Production Planning

      Partner or vendorGurobi OptimizationAccessed Nov 20, 202620 Nov 2026

      Supporting excerpts (3)
      • Each day, planners need to allocate customer orders into 10 production lines that have four primary processing steps (welding, painting, assembly, and testing) while taking into account many additional factors.
      • First tech optimization specialists built a network flow model to address the multi-objective planning problem, and Gurobi was used to solve a sequence of MIP problems generated from the network flow model.
      • Gurobi solves the sequence of MIP problems within 45 minutes, which is significantly reduced from a 9-hour manual planning process using a 5-person team.
    5. Source 5:

      Kaneka: Production Planning Optimization

      Partner or vendorGurobi OptimizationAccessed Nov 20, 202620 Nov 2026

      Supporting excerpts (3)
      • MathCutting was deployed in the polyimide film-producing department at Kaneka’s Shiga Plant to optimize the production planning process as well as the allocation of materials.
      • With MathCutting, Kaneka can rapidly and automatically generate optimal production and cutting plans
      • that enables users to generate optimal cutting plans using the Gurobi Optimizer

    More in Production & Quality

    View all