CNH sets safety stock with predictive analytics in Zedelgem
CNH's combine harvester plant in Zedelgem worked with Superlinear on forecasting and optimization software that suggests safety stock settings for its parts, replacing settings the logistics team kept by hand.
CNHBelgium (Zedelgem plant, West Flanders)Industrial machinery and equipmentPilot
- Scale
- One plant, Zedelgem
- Scenario
- Production parts safety stock optimization
- Business function
- Supply chain and logistics
- Kind of solution
- Forecasting and planning
- Who built it
- Built with a partner (Superlinear)
- Human oversight
- Assists people
- Organization
- Enterprise, 10,000 to 99,999 employees
- AI types
- Machine learning, Optimization
tl;drAn estimated more than 50% fewer missing parts on the line, at the same safety stock value.See the results
CNH, the maker of Case IH and New Holland machinery, uses forecasting and optimization software, built with Superlinear, to suggest safety stock levels at its combine harvester plant in Zedelgem, Belgium1, 2. The software replaces safety stock settings that the logistics team managed by hand1.
The cloud application forecasts supply and demand uncertainty for each part, simulates stock levels, and optimizes where the safety stock budget goes1. It grew out of CNH’s project in the Flanders Make Accelerator Programme1.
In November 2026, Superlinear published the estimated effect at the same total value of safety stock. The frequency of missing parts on the line falls by more than 50%, and express delivery costs fall by more than 10%1.
Before the deployment
Zedelgem is CNH’s Harvesting Center of Excellence, where the plant builds combines such as the New Holland CR112. Its logistics team treated safety stock as the buffer against uncertainty in parts supply, production, and market demand1.
- Parts: CNH must ensure the timely availability of over 30 000 different parts for each production site1.
- Manual settings: The team spent a couple of hours per month on safety stock, so positions were too static for the needs of the moment1.
- High mix, low volume: Common parts are used regularly, while parts for niche configurations have very irregular usage1.
- Long lead times: Suppliers all over the world make it slow to react when future needs are uncertain1.
- Growing complexity: The CR11 launch brought a 30% rise in active parts at the plant2.
When parts ran short, the plant paid for express deliveries or reworked machines once the missing parts arrived1. CNH proposed the project in the Flanders Make Accelerator Programme and chose Superlinear after a selection process1.
What was built
The solution suggests a safety stock setting for each selected part, balancing financial objectives with operational requirements1. Models, an application, and the logistics team share the work:
- Forecasting model: Quantifies drivers of uncertainty, such as delivery delays and short-term demand increases, and estimates their future risk from historical plant data1.
- Simulation: Plays out the effect of those drivers on stock levels and how safety stock would prevent shortages1.
- Optimization model: Weighs the cost of holding safety stock against the value of safety, and allocates the budget over parts1.
- Cloud application: Shows the safety stock suggestions to the right people in CNH’s cloud environment1.
- Logistics team: Takes the safety stock decisions, with the suggestions as input1.
“This solution helps us to transition from a reactive to a more proactive approach. In this way, shortages of stock at the production line can be mitigated before they ever occur, rather than merely preventing a recurrence.”
Rollout
- A workshop with the logistics team on inventory analytics, material planning, and safety stock management, to align definitions with the plant1.
- A data analysis that located the main drivers of uncertainty in the production process1.
- A proof of concept that forecast uncertainties from historical data and recommended safety stock settings1.
- Two more rounds of feedback and improvement with the logistics team at CNH Zedelgem1.
- Integration into CNH’s cloud environment, with added data on the impact of stockouts1.
Technology and architecture
- AI component
- Data
- Trigger or control
- Handoff to people
- Inferred, not documented
Superlinear built the solution with CNH, combining predictive modeling with optimization1. Both the algorithm and the interface run in CNH’s cloud environment1.
| Layer | What they used | Role | Source |
|---|---|---|---|
| Forecasting model | Uncertainty forecasting model | Quantifies drivers of uncertainty and estimates their future risk from historical plant data | 1 |
| Simulation or surrogate model | Stock level simulation | Simulates the effect of the drivers on stock levels and how safety stock would prevent shortages | 1 |
| Optimizer | Safety stock optimization model | Balances the cost of holding safety stock against its value and allocates the budget across parts | 1 |
| Workplace application | Cloud application | Shows the suggested safety stock settings to the logistics team | 1 |
| Cloud platform | CNH cloud environment | Hosts the algorithm and the interface, controls who has access, and supplies the latest data | 1 |
Data and integrations
- Plant data streams: Records of drivers of uncertainty, such as supplier delivery delays and short-term demand increases1.
- Historical plant data: The basis for estimating the future risk of each driver1.
- Stockout impact data: Added data sources show how stockouts of specific parts affect operations, which refines the recommended levels1.
- CNH cloud environment: Gives the right people access to the solution and gives the algorithm the latest data1.
The suggestions most likely reach the plant’s inventory settings through the logistics team, who enter the levels they accept in the inventory management system.
How the four-step method sets safety stock
- The forecasting model quantifies the drivers of uncertainty in the plant’s inventory from various plant data streams1.
- The model estimates the future risk of each driver from historical data available in the plant1.
- The simulation plays out the effect of these drivers on plant stock levels and how safety stock would mitigate shortages1.
- The mathematical model optimizes the suggested safety stock levels for the selected range of parts, in a runtime of less than 1 minute1.
- The cloud application shows the suggestions, and the logistics team takes the safety stock decisions1.
Results
In November 2026, Superlinear published estimates from an analysis with CNH Zedelgem, for inventory-related issues at the same total value of safety stock1.
| Metric | Before | After | Scope and timeframe | Reported by |
|---|---|---|---|---|
| Missing parts on the line | Not disclosed | more than 50% fewer | Zedelgem plant, inventory-related issues, same total safety stock value | Superlinear, estimate1 |
| Express delivery costs | Not disclosed | more than 10% lower | Zedelgem plant, inventory-related issues, same total safety stock value | Superlinear, estimate1 |
- Missing parts on the line: How often a part is missing at the production line. The estimate is a reduction of more than 50%1.
- Express delivery costs: The cost of rushing missing parts to the plant. The estimate is a reduction of more than 10%1.
Superlinear is working with the Zedelgem plant on landing the application in the organization, so that the plant takes future safety stock decisions in a data-driven manner1. It is also developing a next generation of the solution with CNH’s global supply chain team, meant for all CNH plants1.
Lessons learned
The estimates come from redistributing a fixed budget, not from adding stock. The optimization holds the total value of safety stock constant and allocates it across parts by cost and value of safety1.
Working through definitions with the logistics team came first. The workshop made sure that what the data showed matched the plant’s understanding, and two feedback rounds followed the proof of concept1. Lies Pierloot of CNH logistics engineering said the work stayed focused on the plant’s primary objective, reducing missing-part costs and express transport1.
Plant data needed cleaning before the suggestions could be used. A data quality exercise with the logistics team removed irregularities from the solution1.
Trust in the algorithms is still being built. Pieter De Pourcq named it as CNH’s ambition for Zedelgem and for its other plants1.
The figures are Superlinear’s estimates from an analysis with CNH Zedelgem, published in Superlinear’s own customer story while the application was still being landed in the plant1.
Case study scorecard
Sources by publication date
- Organization 1
- Vendors and partners 1
Build this solution yourself
Analysis
What you need
- A history of supply and demand disruptions per part: The forecasting model estimates future risk from historical delivery delays and demand changes in the plant1.
- A cost for each stockout: The optimization weighs the value of safety against holding cost, and stockout impact data sharpened its suggestions at Zedelgem1.
- A logistics team that agrees on definitions: Zedelgem started by aligning inventory concepts with the team, then refined the tool over two feedback rounds1.
Reference architecture
Forecasting and planning
A forecasting and planning solution predicts demand, supply, load, or events from history and outside data, and turns the prediction into a plan such as orders, prices, stock positions, reserve, or crews. Each cycle, forecasting models turn fresh data into a forecast, and an optimizer can turn it into a proposed plan within set targets and limits. Planners decide and enter the plan in the operational system, or they steer an automatic plan through targets and overrides.
- Data feeds and connectors
- Data platform
- Data preparation
- Forecasting models (documented in this case study)
- Optimizer (documented in this case study)
- Approval rules
- Simulation or digital twin (documented in this case study)
- Task agents
- Planning workspace
- Operational system
- Training pipeline
- Forecasting and planning platform
A check mark shows a building block that this case study's sources document.
Open the reference architectureOthers who built it
- Siemens: AI agents draft production plans at Siemens' Erlangen plant. Siemens puts the savings from agent-based production planning at Erlangen at up to 20%.
- Walmart: Walmart plans inventory with AI forecasts and a digital twin. Walmart's 2018 ML forecasts gained ~300 bps in a backtest; one tool has saved more than $55 million.
- Albertsons Companies: Albertsons puts AI replenishment in every fresh department. Afresh's AI ordering ran in all five fresh departments of every Albertsons store by October 2025.
- De Rooy Transport: De Rooy predicts unplanned pickups with machine learning. De Rooy's model is right nine times out of ten on where same-day pickups will be needed.
- AstraZeneca: AstraZeneca calibrates transit lead times with Aera's AI. AstraZeneca's AI now monitors transit lead times on about 2,000 transport lanes worldwide.
- LNER: LNER's machine learning tool flags trains at risk of delay. In the station trial, LNER's delay tool helped avoid over 450 potential delays.
Cite this case study
Enterprise AI Case Studies. "CNH sets safety stock with predictive analytics in Zedelgem." Updated Nov 25, 2026. https://case-studies.ai/case-studies/supply-chain-and-logistics/SC-045-safety-stock-optimization-cnh/
@misc{csai-sc-045,
author = {{Enterprise AI Case Studies}},
title = {{CNH sets safety stock with predictive analytics in Zedelgem}},
year = {2026},
note = {Updated 2026-11-25},
url = {https://case-studies.ai/case-studies/supply-chain-and-logistics/SC-045-safety-stock-optimization-cnh/}
}Sources
The following reporting, and every passage quoted from it, belongs to its publisher, not to this site. Sources and ownership
- Source 1:
Data-driven inventory management: Predictive analytics for safety stock optimization at CNH
Supporting excerpts (39)
CNH needs to ensure the timely availability of over 30 000 different parts for each of their production sites
The Zedelgem plant experiences high costs related to uncertainties in the supply chain, such as supplier delays and varying demand.
expensive interventions are frequently needed: express deliveries of missing parts or delayed reworks of machines once the missing parts are available again.
Together, they developed a solution that combines forecasting and optimization technologies to automatically suggest safety stock settings for CNH
This approach balances financial objectives with operational requirements.
CNH is what is called a high mix - low volume manufacturer
More common parts might be used very regularly, while parts related to niche configurations might have very irregular usage.
factories can have suppliers all over the world, meaning long lead times
However, today, safety stock is managed manually. With a couple of hours per month to manage the safety stock for over 30 000 parts, the current safety stock positions are too static and unable to cover the needs of the moment.
As a participant in the Flanders Make Accelerator Programme, designed to make manufacturing companies more resilient and sustainable at an accelerated pace, they proposed the project idea there.
grant of 11 million euros, complementing the 50 million euros contributed by companies themselves
After a thorough selection process, CNH decided to collaborate with Superlinear, a company specialized in AI, based on their long-term vision for applying predictive methods and optimization technologies in supply chains.
This involved their experience with combining different AI technologies, such as predictive modeling and optimization.
we started by deep diving into their inventory analytics and processes for material planning, inventory management, and safety stock management today in a workshop with the logistics team
it was crucial to align on definitions of different concepts, ensuring that what was found in the data aligned with the understanding in the plant
A following data analysis exercise gave a view on where in the production process most drivers of uncertainties were located that might give rise to process disruption later on.
based on historical data & recommend safety stock settings accordingly
The first promising results led to two additional rounds of feedback and improvement with the logistics team at CNH Zedelgem.
Together, we refined the proof of concept into a solution ready for dynamic inventory optimization in the plant
Both the algorithm and the user interface were integrated into CNH
ensuring access to the solution for the right people and access to the latest data for the algorithm.
additional data sources were integrated, providing more insight into the impact on the operations of stockouts for specific parts. This data allowed further optimization of the recommended safety stock levels.
a thorough data quality exercise was performed with the logistics team to remove irregularities from the solution.
In the current cloud application, you can find safety stock suggestions which are a result of a 4-step inventory optimization method
Examples of drivers are delivery delays and short-term demand increases.
In the second step, we estimate the future risk for these drivers of uncertainty based historical data available in the plant.
Next, we simulate the effect of the indicators on plant stock levels and how safety stock would mitigate stock shortages.
Finally, we use a mathematical model to optimize the suggested safety stock levels for the selected range of parts. The mathematical model balances the costs of holding safety stock with the value of holding safety. This results in the optimal allocation of budget over safety for different parts.
Based on a thorough analysis together with CNH Zedelgem we estimate that, while maintaining the same total value of safety stock, for inventory related issues we can:
Reduce express delivery costs by >10%
Reduce the frequency of missing parts on the line by >50%
With a runtime < 1 minute
This solution helps us to transition from a reactive to a more proactive approach. In this way, shortages of stock at the production line can be mitigated before they ever occur, rather than merely preventing a recurrence.
Pieter De Pourcq, Operational Excellence and Business Transformation Manager at CNH
Throughout this process, they remained focused on our primary objective: reducing costs associated with missing parts and avoiding express transport expenses.
Lies Pierloot - Manufacturing Value Chain Logistics Engineering
Our ambition for the future is to further build trust in these complex algorithms within the company, not only in our Zedelgem plant but also in other plants.
we are currently working with the plant in Zedelgem on landing the application in the organization, allowing them to take future safety stock decisions in a data-driven manner.
we are working with the global CNH supply chain team to develop the next generation of this solution that is meant to be used by all of the CNH plants.
- Source 2:
Supporting excerpts (8)
transformation of its Harvesting Center of Excellence in Zedelgem, Belgium
is celebrating the successful completion of the three-year 'Accelerator' project (2022–2025)
€150 million investment boosting digitalization
challenging the plant to manage a 30% rise in active parts while maintaining efficiency, quality, and operational agility
This investment was also key to the production of the New Holland CR11
CNH co-created the accelerator framework together with Flanders Make
Globally, Case IH and New Holland supply 360° agriculture applications
35,000+ employees form part of a diverse and inclusive workplace
Comments
Start the conversation.
Invited members of the library comment here. Sign in to join the conversation.