GridCARE's AI finds grid room for data centers at PGE
Portland General Electric used GridCARE's AI forecasting and hourly grid modeling to find spare capacity for Hillsboro data centers willing to flex their demand during the grid's few peak hours.
Portland General ElectricUnited States (Hillsboro, Oregon)Electric powerIn production since 2025
- Scale
- Over 80 MW of capacity found for data center load in Hillsboro, Oregon, for 2026
- Scenario
- Grid capacity analysis for large-load interconnection
- Business function
- Energy and asset operations
- Kind of solution
- Forecasting and planning
- Who built it
- Vendor product (GridCARE)
- Human oversight
- Assists people
- Organization
- Enterprise
- AI types
- Machine learning, Optimization
- People served
- nearly 950,000
tl;drPGE found over 80 MW of spare capacity for new Hillsboro data centers on its existing grid.See the results
Portland General Electric (PGE) used GridCARE’s AI forecasting and hourly demand modeling to find room on its existing grid for new data centers in Hillsboro, Oregon1.
The capacity comes from flexibility. Data centers that get the earlier hookup agree to cut their draw from the grid during the few hours each year when demand peaks. They use batteries or onsite generation to do it1, 3.
In October 2025, PGE and GridCARE said they had finished their first joint project. It found over 80 MW of incremental capacity for data center load in 2026, part of more than 400 MW that PGE expects to energize by 20291.
Before the deployment
By October 2025, Hillsboro had 800 MW of data center capacity in operation, on a PGE grid with a total system load of about 4.5 GW2. The town grew into a data center hub because it sits at the mouth of an undersea fiber route between North America and Asia2.
Traditional planning left new data centers with the following problems:
- A long queue: PGE had around 3 GW of active data center load requests2.
- A grid near its limits: Existing load already pushed the Hillsboro transmission network close to its operating limits. The new demand was for data centers in the 50-megawatt to 500-megawatt range3.
- Sizing for the peak: Traditional planning scales the network to serve every customer at peak demand. A data center that wants its full load around the clock waits for new transmission3.
- A few peak days: Data centers used to present as flat, round-the-clock loads that could push the system to its limits during the five or 10 days each year when demand peaks2. Building transmission for those days would take years, cost hundreds of millions of dollars, and leave a grid far bigger than it needs most of the time3.
- Too many variables: A plan has to cover the growth plans of every customer on that part of the grid, for every hour of the year, years ahead. It also has to cover the effect on PGE’s regional transmission network and generation fleet3.
Larry Bekkedahl, PGE’s senior vice president of strategy and advanced energy delivery, said human planners can’t parse all of those variables at once, even with standard planning software3. GridCARE’s CEO, Amit Narayan, said the traditional method works “one project and one scenario at a time”3.
What was built
The solution searches combinations of flexible resources against PGE’s grid to find capacity that data centers willing to flex can use sooner1, 3. The work is divided as follows:
- DeFlex: GridCARE’s patented methodology applies generative AI forecasting, detailed hourly demand modeling, and grid flexibility solutions1. It analyzes 200,000-plus scenarios and contingencies and finds the lowest-cost way to manage the grid’s constraints3.
- PGE planners: Use DeFlex to identify and validate capacity on the existing system1. They then propose commitments to data centers in the Hillsboro area3.
- PGE operators: Manage the customer-sited resources. Years of modernizing grid operations for distributed energy, with real-time data from AI-enabled smart meters, gave them confidence in doing so3.
- Data centers: Commit flexibility, such as a battery, in exchange for a place at the top of the queue3.
“Those data centers that are willing to work with us, if they’re willing to be flexible, we’ll put them at the top of the queue”
Bekkedahl said GridCARE’s tools gave PGE the confidence to bring on data center loads from 50 MW to 500 MW2. The tools also helped the utility and the data centers ramp up load and service in parallel. They helped set operating parameters for service agreements as new computing capacity came online2.
Rollout
The first commitment made public came from Aligned Data Centers, with a battery due to operate the following year7. PGE takes the rest in steps, and Bekkedahl said the utility is “not putting on 400 megawatts tomorrow”3.
Technology and architecture
The following table lists the component of the solution.
| Layer | What they used | Role | Source |
|---|---|---|---|
| Solution platform | DeFlex | GridCARE’s patented methodology, applying generative AI forecasting, hourly demand modeling and grid flexibility solutions, which PGE used to identify and validate capacity on its existing system. It examines combinations of flexible resources across 200,000-plus scenarios and finds the lowest-cost way to manage the constraints | 1, 3 |
GridCARE calls its platform physics-based generative AI1. Narayan said it applies the kind of computing techniques he used in chip design automation to model the interactions of many power-hungry customers across a dynamic, networked grid3. He described the approach as “taking tools that have been in use for many years, that are well understood and well utilized” and moving them into grid planning2.
Inside DeFlex, the forecasting model most likely generates hourly load paths, which the demand model checks against network limits and the optimizer uses to pick the cheapest mix of flexibility.
Data inputs
The analysis uses the following data:
- Customer growth plans: The plans of every customer on the constrained part of the grid, for every hour of the year, years into the future3.
- Flexible resources: The batteries and onsite generation at customer sites, whose combinations the analysis examines1, 3.
- Network impact: The effect of new load on PGE’s regional transmission network and generation fleet3.
- GridCARE’s general data: At its launch in May 2025, GridCARE said its platform draws on grid network models and operational data, utility planning models and planned upgrades, forecasts, interconnection queues, permits, rates, and extreme weather data8.
The first committed project
The Aligned Data Centers battery is the first publicly revealed project in the scope of work behind the 80 MW3. It went through the following steps:
- Through GridCARE’s modeling, PGE identified a combination of flexibility opportunities that could let data centers add 80 megawatts the following year3.
- Aligned and the energy-storage company Calibrant Energy calculated the size of a battery themselves7.
- PGE’s interconnection study validated and specified the size that offsets what the data center demands of the local grid7. The result was a 31-megawatt/62-megawatt-hour battery6, 7.
- Aligned pays for the battery, so PGE’s other customers don’t carry the cost of its growth6, 7.
- Aligned provided the land near its facility, because the constraint was local and the battery had to sit close to the data center7.
- The battery connects on the utility side of the meter, so permitting and construction could move faster. PGE describes it as fully integrated into its grid6, 7.
- PGE can use the battery for other grid needs, such as frequency management and capacity, when the data center doesn’t need it7.
- Once the battery runs, Aligned can expand its computing capacity years sooner than a grid upgrade would allow3.
Results
The results date from the announcement of the first project in October 20251.
| Metric | Before | After | Scope and timeframe | Reported by |
|---|---|---|---|---|
| Incremental capacity for data center load | Waiting years for traditional grid upgrades | over 80 MW | Hillsboro, Oregon, available in 2026 | PGE and GridCARE, estimated1, 6, 2, 3 |
The figures need the following context:
- Incremental capacity: Measures capacity that the analysis found and PGE committed to make available, not load measured on the grid. Bekkedahl said the flexibility opportunities “could allow data centers to add 80 megawatts of additional power use next year”3.
- PGE’s own description: PGE’s presentation to the Data Center Advisory Committee in May 2026 put it as more than 80MW of capacity uncovered in the existing grid, by better understanding how data center flexibility affects the system6.
- The 2029 target: PGE aims to energize more than 400 MW of data center load in Hillsboro by 2029. The figure is a projection that includes the first 80 MW1, 2.
- GridCARE’s figures: GridCARE’s success story for PGE lists >400 MW of grid capacity unlocked and >$10B of value for data center developers5.
Lessons learned
The project produced a customer commitment, not only a model result. Aligned paid for its battery because PGE’s analysis said the data center would connect sooner, and PGE’s interconnection study set the battery’s size3, 7. Aligned’s CTO, Michael Welch, said PGE was able to “model these scenarios and understand them with a high degree of accuracy”, which is a customer’s view and not a measurement3.
Canary Media called the project small next to the gigawatts of planned data center expansions, “not a ton of new computing load”. It also called it a real-world example of a utility planning around a data center’s commitment to cut use at peak. Such public agreements were few and far between at the time3.
The approach doesn’t serve gigawatt-scale campuses. “We do not solve the 2-GW data center problem,” Bekkedahl said of hyperscale campuses that need gigawatts in one place2. He called flexibility “just a bridging strategy”, and PGE will still have to build transmission and generation3.
Flexibility works only where both sides commit. A data center that wants 100 percent of its load at all hours still waits for new transmission, and data centers can’t justify a battery unless the utility commits that it resolves the constraint3. Narayan said risk-averse utilities want proof of concept before investing in non-wires alternatives, and Canary Media noted that not every utility is ready to rely on flexibility. PGE’s years of distributed-energy operations were part of why it could2, 3.
The accounts describe different stages. PGE and GridCARE call it a project they “successfully completed”, while Canary Media describes “a first-of-a-kind project underway” and Bekkedahl said “We want to see it in action before we believe it”1, 3. GridCARE counts >400 MW as unlocked, while PGE gives 400 MW as a target for 20295, 1.
Every capacity figure comes from PGE and GridCARE1, 6. Utility Dive and Canary Media relayed it from interviews with both companies, and in October 2026 Utility Dive relayed it again through Pradeep Tagare of National Grid Partners, an investor in GridCARE2, 3, 4. GridCARE’s >400 MW and >$10B have no stated method, and GridCARE is paid on “megawatts unlocked, which is earned when developers and utilities enter into a contract,” so the megawatts it reports also measure its revenue5, 8.
Case study scorecard
Sources by publication date
- Organization 1
- Vendors and partners 2
- Press, academic, and regulators 5
- 1 undated
Build this solution yourself
Analysis
What you need
To build this solution, you need the following in place:
- Hourly growth plans for every large customer: PGE knew them for the constrained Hillsboro network, years ahead, and could model their effect on its transmission network and generation fleet. DeFlex searches over those inputs3.
- Experience operating customer-sited resources: Years of running batteries and generation at customer sites gave PGE’s operators the confidence to count on them3.
- Customers ready to invest in flexibility: Aligned paid for its battery in exchange for queue priority, with PGE’s interconnection study standing behind its size7, 6.
Reference architecture
Forecasting and planning
A forecasting and planning solution predicts demand, supply, load, or events from history and outside data, and turns the prediction into a plan such as orders, prices, stock positions, reserve, or crews. Each cycle, forecasting models turn fresh data into a forecast, and an optimizer can turn it into a proposed plan within set targets and limits. Planners decide and enter the plan in the operational system, or they steer an automatic plan through targets and overrides.
- Data feeds and connectors
- Data platform
- Data preparation
- Forecasting models
- Optimizer
- Approval rules
- Simulation or digital twin
- Task agents
- Planning workspace
- Operational system
- Training pipeline
- Forecasting and planning platform (documented in this case study)
A check mark shows a building block that this case study's sources document.
Open the reference architectureOthers who built it
In the library
- AI agents draft production plans at Siemens' Erlangen plant Siemens
- Walmart plans inventory with AI forecasts and a digital twin Walmart
- Albertsons puts AI replenishment in every fresh department Albertsons Companies
- De Rooy predicts unplanned pickups with machine learning De Rooy Transport
- AstraZeneca calibrates transit lead times with Aera's AI AstraZeneca
- LNER's machine learning tool flags trains at risk of delay LNER
Cite this case study
Enterprise AI Case Studies. "GridCARE's AI finds grid room for data centers at PGE." Updated Nov 19, 2026. https://case-studies.ai/case-studies/operational-technology/OT-015-grid-capacity-analysis-data-centers-pge/
@misc{csai-ot-015,
author = {{Enterprise AI Case Studies}},
title = {{GridCARE's AI finds grid room for data centers at PGE}},
year = {2026},
note = {Updated 2026-11-19},
url = {https://case-studies.ai/case-studies/operational-technology/OT-015-grid-capacity-analysis-data-centers-pge/}
}Sources
The following reporting, and every passage quoted from it, belongs to its publisher, not to this site. Sources and ownership
- Source 1:
Supporting excerpts (10)
Portland General Electric (PGE) and GridCARE successfully completed their first joint project to accelerate large load interconnections using flexibility for data centers in Hillsboro, Oregon.
This will result in over 80 MW of incremental capacity available for data center load in 2026, part of a total of more than 400 MW that will be energized by 2029.
To identify and validate capacity on the existing system, PGE used GridCARE's patented DeFlex™ methodology, to apply generative AI forecasting, detailed hourly demand modeling, and grid flexibility solutions.
By optimizing the use of flexible resources such as batteries and onsite generation, PGE is able to interconnect multiple data center customers years earlier than initially expected.
By working with GridCARE, we've successfully implemented an AI-based approach that helps us serve fast-growing data center demand while keeping costs low and maintaining system reliability.
positions Portland General Electric as one of the first utilities to utilize AI for large-scale load forecasting
distributes electricity to nearly 950,000 customers
Founded at Stanford's Doerr School
Hillsboro is a major data center hub in the U.S.
through a pioneering physics-based generative AI platform that unlocks gigawatts of near-term capacity from today's grid
- Source 2:
Portland General Electric invests in AI-powered flexibility to speed data center connection
Supporting excerpts (15)
Portland General Electric has freed up more than 80 MW for data center interconnections next year using a new, artificial intelligence-enabled flexibility tool, the utility said Oct. 8.
PGE partnered with the California-based startup GridCARE, which uses AI, detailed hourly demand modeling and optimized flexible resources like batteries and onsite generators to find spare capacity.
Bekkedahl said Hillsboro alone has 800 MW of data center capacity operating today on a grid with a total system load of about 4.5 GW. PGE has around 3 GW of active data center load requests, more than 400 MW of which could energize by 2029, he added.
That's a big change from just a few years ago, when data centers presented as flat, round-the-clock loads that could push the system to its limits during the five or 10 days each year when demand peaks.
We are taking tools that have been in use for many years, that are well understood and well utilized
We do not solve the 2-GW data center problem
But Bekkedahl said GridCARE's tools gave PGE confidence to bring on data center loads ranging from 50 MW to 500 MW. It helped the utility and data centers work together to ramp up load and service in parallel and develop operational parameters for service agreements as new computing capacity came online, he said.
Every megawatt of additional capacity adds $30 million to $40 million in value for large data centers, he said.
Famously risk-averse utilities like to see proof of concept before investing in non-wires alternatives, so this first real-world project is a big boost, he said.
Hillsboro developed into a major data center hub thanks to its position at the mouth of an undersea fiber highway connecting North America and Asia
long a global hub for chipmaker Intel
created an opportunity that was not available to planners previously
The steady deployment of batteries, onsite generation and microgrids over the past decade has
who founded and led virtual power plant platform AutoGrid
The grid tech company was developed out of the Stanford Sustainability Accelerator program.
- Source 3:
Oregon utility tries out a faster, cheaper way to power data centers
Supporting excerpts (43)
Silicon Valley startup Gridcare launched in May with a promise that its artificial intelligence–powered software can help actualize one of the hottest concepts in the electricity sector: data center flexibility.
We've moved from the theoretical to the practical
A first-of-a-kind project underway outside Portland, Oregon, could provide a model for data centers to connect to the grid without driving up utility bills and carbon emissions.
This is our first project where that flexibility really comes into play.
And existing electricity demand is already pushing that grid close to its operating limits in the Hillsboro area.
huge demand for data centers in the 50-megawatt to 500-megawatt range
Under traditional utility planning, the network would have to be scaled up to provide enough power to serve every customer during times of peak demand.
But there are only a few peak hours, during maybe five to 10 days a year, that we need to meet those peaks
Building enough transmission to serve them all would take years, cost hundreds of millions of dollars, and yield a grid that's far bigger than what's needed most of the time.
It has to consider the growth plans of all the customers connected to that part of the grid, during every hour of the year, for years into the future — and then also consider the impact on PGE's regional transmission network and generation fleet.
Human grid planners simply can't parse through all those variables at once, Bekkedahl said, even with the help of standard planning software.
That's where Gridcare came in and helped us model
Through Gridcare's software, PGE identified a combination of flexibility opportunities that could allow data centers to add 80 megawatts of additional power use next year, instead of waiting years for traditional grid upgrades, he said.
Gridcare applies similar computing techniques to model the interactions of lots of power-hungry customers across a dynamic, networked grid, he said.
You have a major combinatorial-explosion issue here
you have to analyze 200,000-plus scenarios and contingencies.
Instead of analyzing one case and one dispatch scenario, which planning teams do
He founded, built, and sold a semiconductor design company called Berkeley Design Automation in the 2000s.
that's typically done in a sequential way, one project and one scenario at a time
We have to look at many different projects, each with its impact on ramp and load, over the next five to 10 years. We have to look at very many different scenarios of flexibility. And we have to do it for every hour of the year.
We're able to take all the sources of flexibility that may exist, and then examine all the combinations and permutations that exist
and find the lowest-cost way to manage those constraints.
Why do we have to live with the old assumptions of designing around worst-case scenarios?
But PGE has been working for years on modernizing its grid operations to support distributed energy and flexibility and bring in real-time data from AI-enabled smart meters, which has given its grid operators confidence in understanding and managing customer-sited energy resources, Bekkedahl said.
With that expertise to back up Gridcare's revelation of the options at hand, PGE has been able to approach data centers in the Hillsboro area to propose mutually beneficial commitments
Those data centers that are willing to work with us, if they're willing to be flexible, we'll put them at the top of the queue
Nope, we're going to want 100 percent
You'll wait for us to build the transmission.
Last month, Aligned Data Centers announced plans to work with energy-storage specialist Calibrant Energy to deploy a 31-megawatt/62-megawatt-hour battery across the street from its Hillsboro data center. It's the first publicly revealed project that's part of the scope of work enabling the 80 megawatts of additional capacity that PGE will be able to energize next year.
Once it's turned on sometime next year, that battery will allow Aligned to expand its computing capacity at the data center years faster than it would have been able to by waiting for PGE to upgrade its grid to supply its peak power demand.
Aligned didn't disclose how many megawatts of increased power demand its expansion will cause
But data centers can't afford to invest in batteries like this without clear commitments from utilities that those investments will in fact resolve the grid constraints preventing them from getting online faster.
They were able to model these scenarios and understand them with a high degree of accuracy, and provide the greatest impact without wasting capacity.
While the utility hopes to interconnect 400 megawatts of expanded data center load in Hillsboro by 2029
There's a stepping-stone process here. We want to see it in action before we believe it.
We're going to have to build out.
we're not putting on 400 megawatts tomorrow
This is just a bridging strategy,
Bringing down the peak, and bringing up the overall utilization of the system, makes it more affordable for all customers.
That's not a ton of new computing load
But public announcements of flexibility agreements between utilities and data center developers are few and far between
Not all utilities are ready to rely on flexibility as an alternative to hard grid upgrades.
Narayan said the startup also has projects underway with unnamed tech giants and data center developers, as well as with utilities including California's Pacific Gas & Electric.
- Source 4:
Utilities turn to AI to manage rising power demand — from AI
Supporting excerpts (4)
For now, most AI deployments in the sector are niche tools designed to support human decision-making on topics like load forecasting and vegetation management.
Barriers to broader utilization include uncertainty over what to do with AI outputs that are uneven or that can't be audited in a highly regulated sector with strict safety and reliability standards.
Tagare pointed to several companies NGP has invested in as examples of AI deployment, including GridCARE, which uses hourly demand modeling to identify available grid capacity. Portland General Electric said its work with GridCARE identified more than 80 MW of capacity for data center connections years earlier than initially expected.
Pradeep Tagare, interim president of National Grid Partners, National Grid's venture capital arm, which invests in AI energy startups.
- Source 5:
GridCARE: Power Acceleration for AI
Supporting excerpts (6)
400 MW unlocked, years ahead
The program takes enormous amount of data, AI analytics. It actually takes compute that exceeds most capabilities.
Maria Pope CEO, Portland General Electric >$10B Value for data center developers >400 MW Grid capacity unlocked for AI infrastructure
GridCARE identified 650 MW of connection capacity on our network in New York for large, flexible loads. This, in turn, reduces the customer connection time and costs.
Zoe Yujnovich CEO, National Grid 650 MW Connected capacity in New York
Collaborating with GridCARE and using advance planning tools enables Portland General Electric to make more informed and faster decisions in bringing this critical infrastructure online with confidence.
- Source 6:
Data Center Advisory Committee
Supporting excerpts (6)
John McFarland, Sr. Vice President, Chief Customer Officer,
PGE partnered with GridCARE to uncover more than 80MW of capacity in our existing grid by better understanding
how data center flexibility impacts the system – with no need for infrastructure.
PGE is partnering with Aligned Data Centers and Calibrant Energy on a first-of-its-kind 31MW/62MWh on-site
owned and paid for by Aligned
that is fully integrated into PGE's grid to maximize grid support
- Source 7:
In a first, a data center is using a big battery to get online faster
Supporting excerpts (10)
On Wednesday, Aligned Data Centers announced it would pay for a new 31-megawatt/62-megawatt-hour battery alongside a forthcoming data center in the Pacific Northwest.
is now entering the construction phase and should be operating sometime next year.
The utility studied just how big the battery would need to be to compensate for challenges imposed on the local grid by the data center.
Aligned and Calibrant had their own calculations, Martin said,
but the validation of that, and the actual specification of that, came out of the interconnection study done on the utility side.
said Phil Martin, CEO at Calibrant, which is owned by Macquarie Asset Management.
Due to the local nature of the power constraint, the battery had to be built close to Aligned's facility; the company ultimately provided the land to host the grid storage installation.
Because Aligned is footing the bill, the utility's other customers won't be forced to pay for the data-center firm's growth ambitions.
the battery will sit on the utility side of the meter. That means the utility can leverage the tech for other grid uses, like frequency management and capacity, when it's not maintaining the flow of power to the data center during otherwise scarce hours.
In this case, Martin said, the permitting and buildout could move faster with the battery connecting to the utility grid instead of directly to the data center.
- Source 8:
Can AI help track down invisible grid capacity?
Supporting excerpts (7)
which emerged from stealth today
which combines generative AI with grid physics
Gridcare maps the utility network across both geography and time, analyzing the grid dynamically and taking advantage of on-site generation and batteries to remove grid constraints and open up new capacity.
The data collected includes grid network models and operational data, existing utility planning models and planned upgrades, forecasts, interconnection queues, permits, rates, and extreme weather data, among other things.
The company then validates its model and assumptions directly with utilities — its partners include Portland General Electric and Pacific Gas & Electric — before using it to help data center developers find available power.
Legacy ways of calculating capacity are overly conservative
megawatts unlocked, which is earned when developers and utilities enter into a contract