How Seattle tested AI pre-screening of building permits
Seattle's permitting teams ran CivCheck, a tool that reads plan sets and checks them against city code, over real housing applications to see whether applicants could fix their errors before submitting.
City of SeattleUnited StatesLocal and regional governmentPilot since Mar 2025
- Scale
- 29 intake and 57 plan review applications
- Scenario
- Building permit application pre-screening
- Business function
- Legal and compliance
- Kind of solution
- Document review and drafting
- Who built it
- Vendor product (CivCheck)
- Human oversight
- Assists people
- Organization
- Public sector
- AI types
- Document AI
- Users
- Roughly 40
tl;drIn Seattle's test, CivCheck caught 87% of the in-scope intake errors that reviewers had found.See the results
In 2025, the City of Seattle tested CivCheck, an AI tool that reads building permit applications and checks them against city code1. The test asked whether the tool could catch the errors that send housing permits back for another round of review1.
The City’s Innovation & Performance team led the test with the Seattle Department of Construction and Inspections (SDCI) from March to October 20251, 2. Historical and in-progress middle housing applications went through the tool, and City reviewers judged every result1.
On intake, CivCheck found 87% of the in-scope errors that SDCI staff had logged1. Its plan review calls matched reviewers’ final decisions 91.7% of the time1. In June 2026, the City published its evaluation and recommended a production pilot in which applicants opt in to pre-screen their applications for completeness1, 2.
Before the deployment
A construction permit application in Seattle is a bundle of forms, documents, and technical drawings, and City staff review it in two stages1, 2. Intake screening checks completeness: whether the application has every document it needs, and whether each document is complete1. Plan review follows. Teams at SDCI, the fire department (SFD), and other departments check the design against the Land Use Code, the Seattle Residential Code, and other codes1.
Both stages run in cycles. The City approves an application or sends it back with corrections, the applicant resubmits, and the loop repeats until every review team approves2. The process had the following results:
- A median middle housing application went through 2.6 intake cycles and 3.7 plan review cycles before approval. Each cycle took about a month of calendar time1.
- In plan review, an average of six teams work in parallel across three or more cycles. The slowest review in a cycle sets its pace1.
- A housing project might need more than 30 approvals from seven departments1.
- Applicants, inexperienced ones above all, often describe feeling blindsided by requirements that they didn’t know applied to them1.
- An internal SDCI analysis found first-pass approval rates of 1% to 15%. It traced 50% to 70% of correction comments to missing information or misunderstandings, not code violations9.
By 2025, permitting was a priority at City Hall. Leah Tivoli, who directs Innovation & Performance, said: “Over the last decade, we have seen the days to issue a permit pretty much triple”8. In June 2025, Mayor Bruce Harrell issued an executive order to speed up permits for housing and small businesses8. His office said that the AI pilot could cut housing review cycles by 50% or more8.
In September 2025, the City’s 2025-2026 AI Plan described the work of the Permitting Accountability and Customer Trust (PACT) team with CivCheck3. The team aimed to cut permit processing times in half by catching errors before applications are submitted3.
“Clarity of requirements, code and regulation complexity, and navigating the city services and processes were really the top three issues.”
What was built
CivCheck reads the documents of a permit application with AI and then runs deterministic checks on what it read1. The AI does the reading, and fixed logic makes each pass or fail1. The City therefore describes the tool as having “a limited use of AI”1. The work is divided as follows:
- AI document reading: Uses multiple AI techniques to read the content of application documents, such as PDF plan sets, and assembles it into structured data1.
- Configured checks: Test that data for missing documents, missing information, and compliance with the relevant code requirements1.
- SDCI reviewers: Verified the results during the test. Users can see the logic behind each suggestion, override it, add clarifications, and make their own determinations1.
- CivCheck staff: Entered the historical applications into the platform and configured the checks1.
- Applicants: Would be the primary users in production. They would load their applications into CivCheck and view the results themselves1.
In the intended use, the applicant runs the application through CivCheck before submitting it2. The tool says whether the application is complete and whether the design complies, and the applicant fixes the errors2. The application then still goes through the normal City review2. Dheekshita Kumar, CivCheck’s co-founder and CEO, described the aim as an applicant handing the City a permit-ready application on the first submission8.
The proof of value ran in a controlled, non-production environment with no applicants in it1. Roughly 40 employees from the Land Use, Zoning, and Ordinance/Structural review teams got access, and at least 14 actively checked CivCheck’s results1. Every pilot user was educated on the City’s Responsible AI policies, and CivCheck passed the privacy review that Seattle IT conducts1. During the test, Clariti, a more established software company, acquired CivCheck1.
Test scope
The test covered middle housing: townhouses, single-family homes, accessory dwelling units, and similar dwellings permitted under the simpler Seattle Residential Code1. Larger buildings fall under the Seattle Building Code1. Middle housing applications make up the majority of new residential permits issued in recent years1. The City kept the test narrow because automated pre-screening can’t check every code for every type of building1. Some designs and requirements are too complex1.
The team configured 34 completeness checks and 67 compliance checks that it thought could be assessed automatically1. The checks cover the following:
- Completeness: Which files an application needs, such as a topographic survey or a geotechnical report. The checks also cover how files are prepared, down to form signatures, sheet stamps, and sheet scales1.
- Zoning compliance: Maximum lot coverage, building height, and front yards, each tied to a section of the 2025 Seattle Municipal Code1.
- Residential code compliance: Fire separation, smoke alarms, basement emergency escapes, and stairway widths from the 2021 Seattle Residential Code, alongside structural, room, and means-of-egress checks1.
Alternatives considered
Several tools on the market advertise similar functions, and the City picked CivCheck over them for the proof of value1. It chose CivCheck for the following reasons:
- Customization: Seattle’s process is uniquely complex, so the City wanted a flexible tool, not an off-the-shelf product that assumed every city permits the same way1.
- A vendor that iterates: The City wanted a vendor willing to explain the technology, answer detailed questions, and iterate with staff1.
- Responsible AI: The City chose CivCheck partly for the company’s alignment with the City’s Responsible AI policies1.
Rollout
After the tests and the feedback sessions, analysis and report writing ran from November 2025 to June 20261.
The report recommended a larger production pilot rather than full production, limited to completeness screening at intake, where the projected impact was highest1, 2. Applicants would opt in, use the pre-screening tool, and then go through the normal process1. The 2026 budget includes funding from the Construction and Inspections Fund for that pilot1.
The City expects the pilot to need an SDCI product manager at 0.75 full-time equivalent (FTE)1. Subject-matter experts would help intermittently to configure and tune the checks1. As of the June 2026 report, the City was still exploring funding and logistical support for tools like CivCheck2, 7.
Technology and architecture
- AI component
- Data
- Trigger or control
- Handoff to people
- Feedback
- Inferred, not documented
During the test, CivCheck ran as an isolated platform1. City staff extracted the application data from Accela, the permit system where SDCI reviewers log rejection reasons, and CivCheck’s staff loaded it into the platform1. Reviewers could submit structured feedback when a determination was wrong or needed clarifying1. CivCheck calibrated its checks to reviewers’ interpretations as the test went on1.
The following table lists the components of the solution.
| Layer | What they used | Role | Source |
|---|---|---|---|
| Solution platform | CivCheck | Pre-screening platform that CivCheck configured for Seattle’s checks, used by SDCI reviewers in the test | 1, 2 |
| Document and OCR model | AI document reading | Reads PDF plan sets and forms into structured application data | 1 |
| Rules and decision logic | Configured checks | 34 completeness and 67 compliance checks run as deterministic logic, each tied to an intake requirement or code section | 1 |
| Review workbench | Review screen | Shows each preliminary pass or fail. Reviewers approve it, mark it as needing correction, or override it | 1 |
| Feedback capture | Structured feedback | Reviewers’ notes on wrong or unclear determinations | 1 |
Data inputs
The test used the following data:
- Historical intake cases: 29 residential applications, with their plan sets and forms, whose intake screening SDCI staff had recently completed1.
- Active plan review cases: 57 residential applications in active plan review1.
- Logged rejection reasons: The 90 rejection reasons that SDCI reviewers had logged in Accela for the 29 intake applications. They formed the baseline for the intake test1.
- Code sections: Sections of the 2025 Seattle Municipal Code and the 2021 Seattle Residential Code that the compliance checks are tied to1.
- Permit performance data: All middle housing projects issued in the 12 months to October 2025, from SDCI’s Construction Permit Performance website. The City used them to model plan review time1.
Integrations
In the production setup that the City describes as ideal, CivCheck would connect to City systems as follows:
- Accela: CivCheck and Accela would share application documents and screening results1.
- City data sources: CivCheck would read from existing sources such as GIS and permit history1.
- Applicant handoff: A full-scale deployment could add an integration that lets applicants push a passed application from CivCheck to Accela. The City puts this at six months or more of work for one of its Accela development teams1.
How the two tests ran
The intake test worked backward from finished work, in the following steps:
- CivCheck employees configured the platform for the 34 checks and ran the 29 original applications through it1.
- CivCheck and SDCI employees compared CivCheck’s screening with the results of SDCI’s screening1.
The plan review test ran CivCheck as a supplemental tool alongside the standard reviewer workflow on 57 applications in active plan review1. For each application, the reviewer did the normal review first and then judged each of CivCheck’s calls. The City then compared CivCheck’s preliminary determinations with the reviewers’ final decisions1.
- AI component
- Data
- Trigger or control
- Feedback
- Inferred, not documented
Results
Both accuracy figures come from the tests that ran between April and August 20251. The time savings come from a model of what would have happened had applicants fixed the flagged errors before submitting1.
| Metric | Before | After | Scope and timeframe | Reported by |
|---|---|---|---|---|
| In-scope intake rejection reasons also found by CivCheck | Reviewers’ own findings | 87% (48 reasons found by both) | 29 historical applications, intake test, 2025 | City of Seattle, pilot1, 7 |
| Agreement with reviewers’ final plan review decisions | Reviewers’ own decisions | 91.7% | 1,262 checks on 57 applications in active plan review, 2025 | City of Seattle, pilot1 |
| Median calendar days to pass intake screening | 54.5 days | 29 days, modeled | 29 projects, pilot configuration, applicants assumed to fix every flagged error | City of Seattle, estimated1 |
| Median calendar days to pass plan review | 161 days | 146 days, modeled | Middle housing projects issued in the 12 months to October 2025 | City of Seattle, estimated1 |
| City staff with a more favorable view of AI | Not disclosed | 71% | Survey of 14 City staff at the end of the proof of value | City of Seattle, pilot1 |
The metrics measure the following:
- Intake rejection reasons: The share of the rejection reasons within the configured checks that both CivCheck and the SDCI reviewers found1.
- Plan review agreement: The share of 1,262 checks where CivCheck’s preliminary call matched the reviewer’s final decision. Reviewers left feedback on 86 of the checks, or 6.8%1.
- Intake time: In the pilot configuration, applicants fix what the 34 checks catch, and manual review catches the rest. The average number of intake cycles falls from 2.55 to 1.75 in that scenario1.
- Full automation: If CivCheck automated every intake check and applicants fixed all completeness errors, the median would fall to 8 days and one cycle. The City cites this as a possible 46-day reduction1.
- Calendar days: Count both the time the City holds an application and the time the applicant holds it1.
- Plan review time: The 146 days assume that CivCheck catches enough corrections to preempt one Zoning and one Ordinance/Structural review. Removing one entire review cycle would bring the median to 117 days1.
- Staff view: Of the 14 City staff surveyed, 86% also agreed with at least one statement about business value. The more frequent users were more positive1.
Lessons learned
The test measured the tool against real work and published the misses with the hits1. Its baselines were the rejection reasons that reviewers had logged in Accela and the reviewers’ final decisions1. The design kept the AI to reading, left each call to fixed logic, and let reviewers see and override the logic1.
Coverage mattered as much as accuracy, because removing a review cycle takes flagging every correction up front2. Of the 90 intake rejection reasons, 35 fell outside the pilot configuration, and CivCheck missed 7 in-scope ones1. In plan review, 6.4% of checks were missed corrections that reviewers required fixed, against 1.9% unnecessary flags1.
Seattle’s own rules were the hardest limit, because automated checks work well for requirements that translate into unambiguous machine logic1. Defining which cases required which documents was sometimes difficult1. CivCheck flagged four applications for a topographic survey that intake screeners had waived at their discretion1.
The City concluded that it has more work to do to make its requirements and processes clearer and less subjective2. CivCheck calibrated its checks during the test to align with reviewers’ interpretations, and its results improved1. The modeled savings assume that applicants fix every error CivCheck catches, and a live tool that lets them proceed with failed checks might save less1.
Reviewers and applicants raised concerns. Multiple reviewers called the interface clunky and said it failed to recognize text in images, and structural reviewers doubted AI on complex engineering1. Applicants warned that checks that weren’t accurate and comprehensive would become “just another hurdle”, and they judged a demo of a non-functional prototype1.
The test ran under a risk acceptance agreement, partly because CivCheck lacked third-party certifications1. A production pilot needs a new security review and the City’s updated AI review1.
The figures are the City’s own, and CivCheck’s staff helped compare its intake results with SDCI’s1. Clariti says that CivCheck identified 83 of the 90 intake rejection reasons, and that its 7 misses came down to four rule types9. The City counts 48 found and 35 outside the configured checks1. Clariti’s 83 most likely adds the two.
Clariti also projects 81.3 days saved per permit at intake, from an average of 90 days in intake9. The City models a possible 46-day reduction from a median of 54.5 days1.
Case study scorecard
- 87% of in-scope intake rejection reasons also found by CivCheck1, 7
- 91.7% agreement with reviewers' final plan review decisions1
- 29 days modeled median time to pass intake screening1
- 71% of surveyed City staff with a more favorable view of AI after the pilot1
- Rules and standards:
- Other1
Sources by publication date
- Organization 3
- Vendors and partners 1
- Press, academic, and regulators 5
Build this solution yourself
Analysis
What you need
This deployment depended on the following, which you need in place too:
- A record to grade the tool against: The rejection reasons that SDCI reviewers log in Accela gave the intake comparison its baseline1.
- Requirements that can be written as unambiguous rules: The checks stumbled where intake screeners used discretion, as with the waived topographic surveys1.
- A vendor that tunes checks for your codes: CivCheck configured and calibrated the checks for Seattle’s codes. The City expects subject-matter experts to help tune them in a production pilot1.
Reference architecture
Document review and drafting
A document review and drafting solution reads a case's documents against a written standard, precedents, or a list of questions and drafts a review, summary, clause, or report with its sources for an expert to finish. The solution pulls the case's documents, and a language model answers each question from the passages that bear on it, with its source. Fixed logic settles what must not vary, and an expert checks the draft against the sources and makes the decision.
- Source system
- Connector to the source system
- Review and drafting platform (documented in this case study)
- Text recognition (documented in this case study)
- Document preparation
- Passage index
- Access control
- Questions and templates
- Drafting model
- Private model endpoint
- Fixed logic (documented in this case study)
- Review workbench (documented in this case study)
- Reviewer feedback (documented in this case study)
- Tests on known cases
A check mark shows a building block that this case study's sources document.
Open the reference architectureOthers who built it
- City of Austin: Adopted Archistar’s AI review for residential building plans in October 2024 after a three-month pilot5. In the pilot, the program was accurate about three-fourths of the time4.
- City and County of Honolulu: Launched CivCheck for residential permit applications in December 20256. It has reported pre-screening cutting reviews from 3.4 to 1.4 cycles per application for single- and two-family projects7.
- City and County of Los Angeles: Launched Archistar’s service on April 30, 2025, after the wildfires5. Property owners can pre-check plans against zoning and building codes before submission5.
In the library
- How Nationwide uses generative AI to summarize claim notes Nationwide
- Merck drafts clinical study reports in days with gen AI Merck & Co.
- AI drafts clinical study reports in minutes at Novo Nordisk Novo Nordisk
- Corona, California speeds building plan review with AI City of Corona
- Denver pre-screens permit applications with CivCheck AI City and County of Denver
- Court strikes down DOGE's ChatGPT screening of NEH grants United States DOGE Service
Cite this case study
Enterprise AI Case Studies. "How Seattle tested AI pre-screening of building permits." Updated Nov 18, 2026. https://case-studies.ai/case-studies/document-intelligence/DI-008-municipal-building-permit-review/
@misc{csai-di-008,
author = {{Enterprise AI Case Studies}},
title = {{How Seattle tested AI pre-screening of building permits}},
year = {2026},
note = {Updated 2026-11-18},
url = {https://case-studies.ai/case-studies/document-intelligence/DI-008-municipal-building-permit-review/}
}Sources
The following reporting, and every passage quoted from it, belongs to its publisher, not to this site. Sources and ownership
- Source 1:
CivCheck AI Pre-Screening Pilot Report
Supporting excerpts (130)
Proof of Value Duration: March 2025 – October 2025
Departments: Seattle Innovation & Performance (IP) and Seattle Department of Construction & Inspections (SDCI)
Sponsors: Leah Tivoli (IP), Marne Zahner (IP), and Eric Berglind (SDCI)
A median middle housing application goes through 2.6 intake screening review cycles before approval.
A median middle housing application goes through 3.7 plan review cycles before approval.
As each cycle takes about one month of calendar time, fewer cycles mean applicants get their permits faster, while staff spend less time repeating the same corrections.
SDCI staff perform Zoning and Ordinance/Structural reviews of the application, with a focus on completeness: does this application have all the necessary documents? Are those documents complete?
multiple teams at SDCI, SFD, and other departments do an in-depth review of the application to ensure the design is compliant with the Land Use Code, Seattle Residential Code, and other building codes.
CivCheck uses multiple AI techniques to read content from application documents such as PDF plan sets and assemble that content into structured data.
CivCheck performs deterministic checks on that data to see if all documents are included, if the documents are missing information, and if the design complies with relevant code requirements.
The term "proof of value" (PoV) means that this project was a pilot of a new technology done in a controlled, non-production environment.
Scale to larger scale production pilot
Projected impact is higher for the intake screening phase; as a result, we recommend a production pilot focused on pre-screening application completeness.
This report summarizes the results of the pilot and details the pilot's alignment with the City of Seattle's Responsible AI Policy using the criteria laid out in the 2025-2026 AI Plan.
March 2025: kickoff and scoping.
April – July 2025: testing of compliance pre-screening.
August 2025: testing of completeness pre-screening.
September – October 2025: gathering feedback from staff and outside stakeholders.
November 2025 – June 2026: analysis and report writing.
In a production use, the primary users would be applicants: applicants would load their applications into CivCheck and view the results themselves.
CivCheck employees entered historical construction permit applications into CivCheck's platform. SDCI employees used the platform to view and verify the results.
Roughly 40 employees from teams that do Land Use, Zoning, and Ordinance/Structural reviews were given access; at least 14 actively participated in checking CivCheck's results.
Automated pre-screening cannot check compliance with every code for all types of buildings: some building designs and code requirements are just too complex.
The PoV focused on smaller "middle housing" dwellings (townhouses, single family homes, ADUs, etc.) that are permitted under the simpler Seattle Residential Code
as opposed to the Seattle Building Code used for larger buildings
These types of applications make up the majority of new residential construction permits issued in recent years.
The PoV included 34 completeness checks and 67 compliance checks that the group thought could be automatically assessed
For intake screening, CivCheck's automated review identified 87% of the errors identified by manual reviewers.
Automated checks work well when they're checking requirements that can be easily translated into unambiguous machine logic.
Even for simple buildings, it is not clear how much of the Land Use Code and Seattle Residential Code requirements could be accurately assessed with automated checks.
while configuring CivCheck, it was sometimes difficult to define which cases required which documents.
To maximize the impact of automated pre-screening, the City needs to clarify its requirements so that they can be translated into clear logic.
the checks must be accurate and comprehensive, or they risk being seen as "just another hurdle" in an already-lengthy process.
Applicants would be able to opt in; they would use the pre-screening tool and then go through the normal process.
a possible 46-day reduction in intake screening duration.
we compared the actual duration and number of cycles to theoretical scenarios in which a pre-screening tool had helped the applicant fix errors in advance of submitting.
For intake screening, the PoV looked at 29 projects that had already passed intake before the pilot started
considers CivCheck as configured for the pilot: 34 completeness checks were performed, representing a subset of the checks done by staff in intake.
considers CivCheck if it were configured to automate all of the checks in the intake screening.
we considered all "Middle Housing" projects issued in the 12 months leading up to October 2025, as reported on SDCI's Construction Permit Performance website.
models the impact of CivCheck catching enough corrections up front to preempt one Zoning and one Ordinance/Structural review.
models the impact of CivCheck removing one review of each type, i.e. removing one entire review cycle.
The impact estimates assume applicants fix all errors caught by CivCheck.
If the actual implementation allows applicants to proceed with some failed checks, the impact may be less than estimated.
requiring a 100% pass may frustrate users
Intake Screening: Median calendar days to pass intake screening 54.5 29 8
Intake Screening: Average # of intake review cycles 2.55 1.75 1
Intake Screening: Average # of intake reviews (Zoning + Ordinance/Structural) 3.86 3.34 2
Plan Review: Median calendar days to pass plan review 161 146 117
Plan Review: Median # of correction cycles to pass plan review 3.72 3.39 2.72
Calendar days include both City Control and Applicant Control periods.
Plan review is a complex process, with an average of 6 review teams working in parallel across 3+ cycles.
the overall duration only shortens if you shorten the specific review that is the "bottleneck" for that cycle; shortening other reviews has no impact.
CivCheck employees configured their platform for 34 checks, then ran the 29 original applications through the platform.
CivCheck and SDCI employees compared the results of SDCI's screening with CivCheck's screening.
90 total rejection reasons were logged by SDCI reviewers in Accela records.
35 rejection reasons were related to checks that were not included in the pilot configuration.
48 rejection reasons – 87% of in-scope reasons – were identified by both CivCheck and the SDCI reviewers.
7 in-scope rejection reasons were not caught by CivCheck.
4 applications were flagged by CivCheck as needing a topographic survey, but not flagged by the SDCI reviewers.
All 4 were cases where a topographic survey was typically required, but the intake screener used their discretion to exempt the requirement for the project.
For example, one project was on a site with steep slopes. Normally, those slopes require a survey.
In this case, the project's scope was confined to within an existing basement
For 57 residential permit applications in active plan review, CivCheck was used as a supplemental pre-screening tool alongside standard reviewer workflows.
SDCI reviewers conducted their normal Zoning and Ordinance/Structural reviews and then used CivCheck's platform to see its preliminary pass/fail determinations for all 67 configured checks.
Reviewers clicked "approve" when they agreed a requirement was met.
Reviewers clicked "needs correction" when they agreed a requirement was not met.
Reviewers could submit structured feedback if CivCheck's determination was incorrect or required clarification.
1,262 Zoning and Ordinance/Structural checks were performed.
Reviewers provided feedback on 86 checks (6.8%).
For the remaining 1,176 checks (93.1%), no feedback was provided, implying agreement with CivCheck's determination.
CivCheck's preliminary determinations were compared to reviewer's final decisions
Overall Accuracy: 91.7%
False Positive Rate: 6.4%
CivCheck indicated a pass where reviewers required correction (missed correction)
False Negative Rate: 1.9%
CivCheck indicated a fail where reviewers approved (unnecessary flag)
Over the course of the proof of value, CivCheck calibrated their checks to better align the platform with reviewers' interpretations and saw improved results.
A survey with 14 City staff involved in the Proof of Value showed that 71% had a more favorable view of AI after the pilot than when it started.
86% agreed with at least one of the business value statements, with more frequent users of CivCheck being more positive.
Multiple reviewers directly reported that the CivCheck interface is clunky, defaults to irrelevant documents, requires extra navigation, and fails to recognize text in images.
greater skepticism from structural reviewers about AI's ability to assess complex engineering
less consensus that faster intake alone shortens total project timelines
Participants also noted that a single stalled permit or review can delay an entire project
Users are broadly supportive of the CivCheck Pilot and of pre-screening tools.
The tool has a limited use of AI: the core logic of the checks is deterministic, not probabilistic.
users can see the logic behind a suggestion, override automated suggestions, add clarifications, and make independent determinations.
CivCheck was selected in part because of the company's alignment with the City's Responsible AI policies.
100% of users were educated on City's Responsible AI policies.
a housing project may need 30+ approvals from 7 departments. Inexperienced applicants often struggle to navigate these multiple processes.
they often describe feeling blindsided by requirements they didn't know existed or didn't realize were applicable to their project.
CivCheck passed the City's privacy review process conducted by Seattle IT.
The proof of value was done under a risk acceptance agreement between the City and CivCheck, partially due to CivCheck's lack of third-party certifications.
CivCheck was acquired by Clariti, a more established software company
In order to proceed with a production pilot, CivCheck would need to pass a new security review and the updated AI review.
application data was extracted from Accela by City staff and loaded into CivCheck by their staff.
In an ideal production use, data integrations would allow CivCheck and Accela to share application documents and screening results. In addition, CivCheck would be able to read from existing City data sources like GIS and permit history. However, the proof of value did not explore integration.
SDCI product manager: 0.75 FTE to project manage the deployment, monitor progress, and analyze results.
Intermittent support from SMEs to configure and tune the checks.
build an integration with Accela that lets applicants push a
this is likely a 6+ month project for one of the City's Accela development teams.
Exact cost structure has not been agreed to.
The 2026 budget includes funding from the Construction and Inspections Fund for a production pilot.
Some jurisdictions partially offset their AI pre-screening costs via direct charges to applicants.
While several tools on the market advertise similar functions, the City selected CivCheck for the proof of value based on the following:
We sought a flexible tool, not an off-the-shelf solution that assumed all cities permit the same way.
Seattle's process is uniquely complex and acknowledging that was critical to success.
Seattle needed a vendor willing to explain the technology, answer detailed questions, and iterate with us.
conducted feedback sessions with 20 external stakeholders in September and October 2025.
The demos provided to participants during the feedback sessions used a non-functional prototype: while the interface and features were shown in full, AI capabilities were not active or running.
applicants were not shown the Code Check portion of CivCheck, which conducts compliance checks.
Demos focused on the Upload Files, Project Details, File Check, and Intake Check sections.
Due to resource limitations, the proof of value was not fully configured to reflect a production implementation
the City should position any AI-assisted pre-screening tool as supportive aid, not an enforcement mechanism or building code interpreter.
Applicants emphasized the tool should be opt-in until proved out, citing concerns it could add work for experienced users.
I would not like to live in a future where we end up doing work that SDCI does now
Maximum Lot Coverage 2025 Seattle Municipal Code 23.44.010.C
Building Height 2025 Seattle Municipal Code 23.44.012
Front yard 2025 Seattle Municipal Code 23.44.014
Fire Separation Distance (non-sprinklered) 2021 Seattle Residential Code R302.1
Smoke Alarms 2021 Seattle Residential Code R314.3
Emergency Escapes: Basements 2021 Seattle Residential Code R310.1
Stairway: Minimum width 2021 Seattle Residential Code R311.7.1
Plan Review Checks: Structural
Plan Review Checks: Room Requirements
Plan Review Checks: Means of Egress
Topographic Survey • Geotechnical Report
Form signatures • Sheet stamps • Sheet scales
some applicant feedback reflects features not demonstrated
during the pilot, including capabilities that already exist within the CivCheck platform.
- Source 2:
Supporting excerpts (19)
When someone applies for a construction permit, they submit a complex application containing multiple forms, documents, and technical drawings.
Applications often take several cycles of review before they are approved; each review cycle adds a month or more to the process.
first the applicant submits their materials, then the City teams review and either approve it or send it back with corrections. This cycle repeats until all review teams approve.
Starting in March 2025 and in partnership with the Seattle Department of Construction and Inspections (SDCI), Innovation & Performance (IP) conducted a proof of value study with CivCheck
an applicant planning a small residential project—like a townhouse, single-family home, or accessory dwelling unit—runs their application through CivCheck before they submit their application to the City.
The tool gives the applicant feedback on whether their application is complete and if their design is compliant.
The applicant can then fix the errors in their application before submitting it to the City.
Once the applicant submits their application, it still goes through the normal City review process.
Applicants would save the most time if pre-screening eliminates an entire review cycle.
Removing a review cycle requires the pre-screening to flag every single correction up front.
If the pre-screening only catches some of the corrections needed, then the applicant may end up going through the same number of review cycles as they would without pre-screening.
Based on this testing, we believe we can achieve higher coverage of completeness checks than compliance checks.
Completeness checks look at a smaller set of requirements related to City processes and document standards.
checking compliance requires comparing the design to the thousands of requirements in Seattle's building codes.
Some of those requirements are conceptually complex and likely difficult to automate.
Simplifying the City's own codes and processes would make it easier to automate both completeness and compliance checks in the future.
It also demonstrated that the City has more work to do to make our requirements and processes clearer and less subjective.
Based on our findings, we recommend a production pilot for pre-screening application completeness.
While we explore options for funding and logistical support to leverage new tools like CivCheck in our construction permitting process
- Source 3:
Mayor Harrell Launches New Responsible AI Plan and Community Innovation Hackathon Series
Supporting excerpts (3)
Today, Mayor Bruce Harrell announced the City of Seattle's ambitious 2025-2026 AI Plan
The Permitting Accountability and Customer Trust (PACT) team launched by Mayor Harrell in June is working with CivCheck to cut permit processing times in half by catching errors before applications are submitted.
Our new plan ensures we lead with our values, using AI to improve services, empower employees, and speed up processes like permitting
- Source 4:
Austin will use AI to evaluate residential construction plans
Supporting excerpts (3)
José Roig, who heads Austin's Development Services Department, said using AI could help speed up this process.
Roig said the program was accurate about three-fourths of the time.
It sometimes got tripped up by the myriad rules governing trees and flooding.
- Source 5:
Municipalities tap AI for permitting
Supporting excerpts (4)
Austin officially adopted the technology in October 2024 following a three-month pilot, and the city and county of Los Angeles launched the service on April 30, according to Gov. Gavin Newsom's office, following wildfires that devastated the region.
Austin has begun using Archistar for residential permits, with plans to expand into other areas.
Archistar's technology uses computer vision, machine learning and automated rulesets to instantly check designs against local zoning and building codes
With it, property owners can pre-check plans before submission to ensure validity and prevent delays.
- Source 6:
New AI software tool, CivCheck, comes to DPP
Supporting excerpts (4)
We are very excited to integrate AI into the building permit review process with the launch of CivCheck
Though the software is currently optional to use, officials say it will eventually become required
It's currently available for residential permit applications, including single-family, two-family and duplex projects
The software does not replace the DPP's official review nor does it guarantee permit approval.
- Source 7:
Cities turn to AI to speed housing permitting
Supporting excerpts (5)
Seattle also crunched the numbers during its pilot of CivCheck and found it was 87 percent accurate on application completeness checks and 92 percent accurate on design-compliance checks.
CivCheck showed an approximate 50 percent reduction in average days for intake review of permits and a 35 percent reduction in correction cycles per review.
As of its June 2026 report, the city was still exploring funding and logistical support for tools such as CivCheck.
So far, Honolulu has reported CivCheck pre-screening has dropped permit reviews from an average of 3.4 review cycles per application to 1.4 cycles for single- and two-family residential projects.
When you can remove three, four or five review cycles of feedback and turn that into one review cycle, that's where you start to see material improvements in permit turnaround times
- Source 8:
Seattle to deploy AI to speed up housing and small business permit process
Supporting excerpts (7)
Seattle Mayor Bruce Harrell issued an executive order on Monday intended to speed the permitting process for housing and small businesses in the city
The mayor's office says the AI pilot program, which falls under the city's Responsible Artificial Intelligence policy, could cut housing review cycles by 50% or more.
A pilot AI program began in April, and public roll-out of the technology is expected in 2026.
The city is working with Boston- and Chicago-based CivCheck, which was founded in 2023
The idea is that the applicant is able to essentially hand the city a permit-ready application in the very first submission
Over the last decade, we have seen the days to issue a permit pretty much triple
Clarity of requirements, code and regulation complexity, and navigating the city services and processes were really the top three issues.
- Source 9:
How Seattle is Using AI to Address the Root Cause of Permit Delays
Supporting excerpts (8)
ran an internal analysis that found first-pass approval rates ranged from 1 to 15 percent, and that 50 to 70 percent of all correction comments stemmed from missing information or misunderstandings rather than actual code violations.
For intake specifically, CivCheck identified 83 of 90 rejection reasons across 29 applications, missing only 7 due to ambiguous definitions of when certain checks applied.
Those 7 misses corresponded to just four unique rule types, each resolvable with under an hour of configuration.
Modeled against actual intake performance, the projected potential time savings came to 81.3 days per permit in the intake phase alone.
An average of 4.5 intake review cycles per permit, with intake alone taking 90 days on average
Across both phases, CivCheck's AI aligned with human reviewer determinations 92 percent of the time.
25,200 staff hours saved annually at permit intake
Scaled across Seattle's annual volume of approximately 8,400 construction permits